Question to the Minister of Education
Minister's Answer
There are currently seven capital projects in East Antrim awaiting completion.
The current position of these projects is as follows:
School | Current Position |
Islandmagee Primary School | Project is in the construction stage, with completion anticipated in summer 2024. |
St Killian’s College | Project is in the design stage and a revised planning application is to be submitted in the coming months. |
Belfast High School | The project was announced in March 2022, however was paused in April 2023. |
Carrickfergus Academy | Procurement of an Integrated Consultant Team for the project has commenced, following the re-start of the project in February 2024. |
Larne Grammar School | The project was announced in March 2022, however was paused in April 2023. |
Larne High School | The project was announced in March 2022, however was paused in April 2023. |
Ulidia Integrated College | Project is in the construction stage with completion anticipated by the end of 2024. |
Projects will continue to advance in planning and design but will only be permitted to progress to construction when affordable within the wider education budget context. As I have previously stated, it is my intention to continue to make the case for significant additional and sustained capital budget to invest right across the schools’ estate.
Comments